Concordia Project updates

Current phase

Docked at “Molo Ex Superbacino” dock and dismantling of decks 14 to 2


Foto2

STATUS UPDATE 25TH AUGUST 2016

With the removal of the last two sponsons occurred yesterday, preliminary operations for transfer the wreck to the Dry Dock no. 4 are concluded. By making watertight the deck 0, allowing to restore autonomous buoyancy to the hull, the wreck is moving towards the final stage of the operations of the Concordia dismantling and recycling … Continued


Shiprecycling_0716

STATUS UPDATE 27TH JULY 2016

Concordia dismantling and recycling operations are progressing and the about 200 technicians are working on the wreck and cutting decks – from 3 to 1 – while the decks from 14 to 3 (partly) have already been removed. As the weight of the wreck becomes lighter, it has been possible to remove 21 sponsons so … Continued


Concordia ph-merlo 150813-9839

STATUS UPDATE 19TH MAY 2016

Concordia dismantling and recycling operations are quickly progressing.   About 200 technicians are working on the wreck and cutting decks – from 3 to 1 – while strip out operations continue on decks 1 and 0 to remove internal fitting.   As the weight of the wreck becomes lighter, it has been possible to remove … Continued


Concordia ph-merlo 160122-0403

STATUS UPDATE 6TH April 2016

Concordia dismantling and recycling operations are quickly progressing and the deck 0 has re-emerged over the past weeks. About 200 technicians are now working on the wreck and cutting decks – from 5 to 3 – while strip out operations continue to remove internal fitting, with work about to be completed on deck 2 and … Continued


A consortium