STATUS UPDATE 6TH April 2016

Concordia ph-merlo 160122-0403
Concordia dismantling and recycling operations are quickly progressing and the deck 0 has re-emerged over the past weeks. About 200 technicians are now working on the wreck and cutting decks – from 5 to 3 – while strip out operations continue to remove internal fitting, with work about to be completed on deck 2 and … Continued

STATUS UPDATE 16th FEBRUARY 2016

Concordia ph-merlo 160112-4509
Concordia dismantling and recycling operations are quickly progressing and the deck 0 is about to re-emerge. About 200 technicians are now working on the wreck and cutting decks – from 5 to 3 – while strip out operations continue to remove internal fitting with work about to be completed on deck 2 and 1. As … Continued

STATUS UPDATE DECEMBER 23th 2015

Genova ph-merlo 151027-3805
Concordia dismantling and recycling operations are quickly progressing. About 200 technicians are now working on the wreck. Cutting has reached deck 5 while strip out operations continue to remove internal fitting with work about to be completed on deck 2 and beginning on deck 1. As the weight of the wreck becomes lighter, it is … Continued

CONCORDIA PROJECT UPDATE- NOVEMBER 11th 2015

Genova ph-merlo 151027-3772
The dismantling activities are concerning the decks 8 and 7 of the wreck, at the same time, the stripping activities – ie removal of the interiors – are focusing on decks 2 and 1. More than 7,000 tons of steel have already been sent to be recycled. Currently there are about 200 workers involved in … Continued

STATUS UPDATE OCTOBER 20th 2015

Concordia Cors
Concordia dismantling and recycling operations are quickly progressing. About 200 technicians are now working on the wreck. Cutting has reached deck 9 while strip out operations continue to remove internal fitting, with work about to be completed on deck 3 and beginning on deck 2. As the weight of the wreck becomes lighter, it is … Continued